Roll-ups and hierarchy ​

Jira work is a tree: initiatives hold epics, epics hold stories, stories hold sub-tasks. Roll-ups add up everything under each issue, so an epic’s story points include its stories’ points.

The default hierarchy ​

Out of the box, levels follow Jira’s own hierarchy:

Initiative › Epic › Story › Sub-task

Each level finds its parent through Jira’s parent field. Add a level, such as Epic, to Rows to group issues under it.

Your own levels ​

Under Edit layout → Options → Hierarchy you can change the levels:

  • Name each level as your teams call it.
  • Holds says which issues belong: a Jira hierarchy level, or a list of issue types.
  • Parent says how a level finds its parent in the level above: Jira’s parent field, or an issue link such as “is implemented by” in either direction.

So a Theme level above initiatives, linked by “relates to”, works just like the built-in levels.

How roll-ups count ​

With Roll up the hierarchy on (under Options → Show), each issue counts towards every level above it:

  • An epic’s story points include its stories and their sub-tasks.
  • An issue under two parents counts once under each, but only once in the grand total.
  • Issues with no parent in scope appear under No Epic (or the level’s name).
  • Links that loop back on themselves are ignored, so nothing counts twice.

Turn it off to count only issues that sit directly at each level.

The issue tree view ​

Issue tree shows every issue under its parent with rolled-up values, status and assignee. Parents that are only there for grouping, or that your filters exclude, are shown dimmed.